Ahmedabad–Dholera Expressway Nears Completion | Key Bottleneck Work Progresses Rapidly
Introduction Ahmedabad–Dholera Expressway apne final stage par pahuch gaya hai—108 km ke stretch mein se approx 98% ka kaam complete ho chuka hai. Ye Gujarat ke infrastructure growth ka ek landmark moment hai. Ye vital corridor state ke capital region ko Dholera SIR se connect karta hai, aur travel time 40–45 minutes tak reduce hone wala hai—connectivity aur industrial momentum dono ko boost mil raha hai. 🔍 Key Developments ✅ Major Bottleneck Clearance Juval Rupavati village ke paas 66 kV substation ka relocation complete ho gaya hai—ye alignment ka ek bada obstruction tha jo ab clear ho chuka hai. 🚆 Railway Overbridge (ROB) Works Expressway Western Dedicated Freight Corridor (WDFC) aur Bhavnagar railway line ko cross karta hai. Steel bridge erection dono jagah complete ho chuka hai; ek side par bitumen laying ho gayi hai, doosri side par expansion joint ka kaam chal raha hai. 🛣️ Interchange for Dholera Activation Area Dholera Activation Area ke access ke liye interchan...